Feasibility and Schematic Design Phases
The purpose of the Feasibility Study phase is for Norton and the
Massachusetts School Building
Authority (MSBA) to explore potential solutions to Norton High School's
facility problems that were identified and verified in prior phases of the
school construction, renovation and repair grant process. Possible solutions to
be explored may include repairs to building systems, renovation, and/or a
building addition. The MSBA is interested in developing solutions that are
educationally appropriate and cost effective. Prior to conducting the
Feasibility Study, the district and the MSBA will need to agree upon an
enrollment projection, scope, cost and schedule of the study. The District will
need to articulate its educational program needs, using the MSBA standard forms,
in order to determine the types of spaces needed to deliver the required
educational program. After analyzing possible solutions, if the District
and the MSBA agree on a preferred option, schematic drawings and a cost estimate
for that option will be developed. The District will need to demonstrate how it
intends to finance the initial capital cost of the agreed upon preferred
solution as well as financially support the staffing and operation over time.
These guidelines are written to provide information to assist the district and
the study designer in understanding the process and the expectations of the MSBA.
The following
professional services are required to participate in this grant program, at a
cost
up to $600,000 for this initial
phase:
What will the Feasibility Study and Schematic Design funds pay for?:
MSBA Approval Requirements
Collaboration with the MSBA throughout the entire process of conducting a
Feasibility Study is essential in order to ensure that the conclusions reached
are in the best interests of the District as well as those of the MSBA.
The Feasibility Study Agreement will allow a District to begin receiving
reimbursement from the MSBA for the MSBA’s share of eligible study expenses
through the MBSA’s Pro-pay system. In order to ascertain MSBA input and approval
throughout the study process, the District is required to secure MSBA
concurrence and/or approval at the following study milestones before proceeding
to the next milestone. Note that some of the approvals to move to the next
milestone require a vote of the MSBA Board of Directors.
• MSBA approved Enrollment Projections generated through the
MSBA’s on-line enrollment projection system (Norton High School = 700 students)
• MSBA Space Summary Template of the current facility
• Scope, Cost and Schedule for the Feasibility Study
• Preliminary Program
• Budget Statement for Educational Objectives• Development of Alternatives
• Preliminary Evaluation of Alternatives
• Final Evaluation of Alternatives
• Recommendation of Preferred Schematic Design
• Budget Statement for Preferred Schematic Design
• Final Design Program for Preferred Schematic Design
• Preferred Schematic Design and proposed Total Project Budget
Study Requirements
Due to the variety and nature of proposed appropriate solutions (e.g.,
non-construction alternatives, repairs to a single building system, renovations
to the entire facility, an addition), each study will vary as to the specific
requirements, scope, cost and schedule. The particular requirements, scope, cost
and schedule of a study will be outlined in the Feasibility Study Agreement
between the District and the MSBA. The requirements may be based on many factors
including the MSBA’s due diligence efforts as well as any meetings or
conferences that may have occurred between the District and the MSBA. The
following listing of activities should be considered the minimum requirements.
-
Justification
-
Statement of Problem
-
Objectives, Process and Schedule of Study (work plan)
-
Existing Conditions
-
Educational Program, Standards and Policies
-
Preliminary Design Program
-
Development of Alternatives
-
Preliminary Evaluation of Alternatives
-
Develop Budget Statement for Educational Objectives
-
Final Evaluation of Alternatives
-
Recommendation of Preferred Schematic Design
-
Final Design Program for the Preferred Schematic Design
-
Preferred Schematic Design
Download the full Feasibility Study and Schematic Design
documents:
Feasibility Study and Schematic Design Presentation
Feasibility Study Guideline
Feasibility Study Work
Plan
Schematic Design Work
Plan
|